A B C D E F G H I J K L M N O P Q
1
BILL OF QUANTUTIES OF TWO BEDROOM OFFICE FOR SLMET ,MATTRU JONG.
2
TWO BEDROOMS OFFICE BLOCK
3
S/N DESCRIPTION QUANTITY UNITY UNIT COST AMOUNT
4
1 SUBSTRUCTURE
5
(NOTE: All Quantities in this section are provisional and
are subject to re-measurement)
6
7
Site Clearance
8
a Clear the whole site of bushes and shrubs, remove debris from site 1 Item
9
10
Excavation
11
b Excavate over site, average 150cm deep, to remove top
soil and vegetable matter, dispose off excavated materials
3.8 m3
12
Excavating, starting at the site strip level, maximum
depth not exceeding 1000mm
13
c Trenches to receive concrete footing in foundations 2.9 m3
14
Excavating, starting at the site strip level, maximum
depth not exceeding 3.0m
15
d Pit (1Nr) 51 m3
16
17
Excavating rocks in trenches and pits n.e. 1m
18
c Laterite rocks (PROVISIONAL) 20.5 m3
19
20
d Filling and disposal of excavated materials
21
22
Disposing and compacting in layers, maximum 100mm
thick selected materials arising from excavations to
23
e Excavate as back filling materials 3.5 m3
24
25
f Make up levels under floors 15.5 m3
26
27
Selected hardcore (ball stones) materials, obtained off, to
28
g Make up levels under floors 225mm thick average, well
rammed and leveled to an even surfac
22 m2
29
30
h Dispose of surplus excavated materials 50.1 m3
31
32
Concrete Work in Foundations
33
34
Plain in-situ concrete (1:3:6 - 1.5" aggregate)
35
i Footing in trenches 250mm thick (average) by 600 wide 10 m3
36
37
j Column footing in trenches 250mmthick and
600mmX600mm
2.5 mm
38
39
k Beds, 250mm interspatial within the pit to carry dividing
walls
5 mm
40
41
Reinforced Concrete Work in Foundations
42
43
Reinforced in-situ concrete (1:2:4 - 3/4" aggregates)
44
l Upstand / baffle wall beams to receive suspended slab 5.2 m3
45
46
m Suspended slab over Pit 150mm thick including cutting
holes for 100mm diameter vent pipe and 650 x 650
openings
5.1 m3
47
48
n 3# Substructure columns 225x225 at each lengthier of the
pit
2.8 m3
49
50
o Ring beam at mid section pit all over wall substructure
wall
8 m3
51
52
Plain round mild steel bar reinforcement, BS 4449; in
foundation straight and bent bars, in
53
p Suspended slab, over pit 12mm diameter as mesh
150X150; extending to the privacy wall externally
50 m3
54
55
q Ring beams 12mm diameter and baffle 95.5 kg
56
57
r Column 12mm diameter @150 square grid 94.2 kg
58
59
s Edges of beds, not exceeding 100mm high 10.5 m
60
61
t Edges of beds, exceeding 100mm high BUT <175MM 18 m
62
63
u Soffits of suspended slab 13.5 m2
64
65
v Sides of upstand beams 8.34 m2
66
67
w Allow for boxing m/h openings 150mm high 12.5 m
68
69
Precast reinforced concrete removable slab
70
x 800 x 800 x 100mm thick 6 Nr
71
72
Blockwork in Foundations
73
74
Precast sandcrete solid blocks, bedded and joined in
cement mortar (1:6), in
75
y Pit 225mm thick walls 50 m2
76
z Allow to make 200 x200 opening between chambers in blockwork 12 Nr
77
78
79
Finishings in Foundations
80
81
Cement and sand (1:6) render, smooth troweled finish to
82
aa Blockwall and concrete surfaces, 12mm thick externally 45 m2
83
84
ab Provide 1:4 sand cement plastering to the internal walls
of the lining (pit)
78 m2
85
86
ac Rendered surfaces externally 20.6 m2
87
Total SUBSTRUCTURE Carries to Summary -
88
SUPERSTRUCTURE
89
90
2 CONCRETE WORK -
91
-
92
Reinforced in -situ concrete (1:2:4 - 20mm aggregate), in
93
a Horizontal beams 0.9 m3
94
95
b Lintels (beam above the doors) 0.15 m3
96
97
Precast reinforced concrete (1:2:4 - 20mm aggregate),
including formworks, reinforcement bars, hoisting into
position and pointing in cement mortar (1:6)
98
c Provide and fix a well designed proprietary drop pit
eastern type ceramic toilet fitting.
4 Nr
99
100
Plain in-situ concrete (1:3:6 - 20mm aggregate), on
101
d Gable walls to support purlins 0.2 m3
102
103
Plain round mild steel bar reinforcement BS 4449,
straight and bent bars, 12mm diameter, in
104
e Horizontal beams 8.5 kg
105
106
f Lintels(beam above the doors) 7.5 kg
107
108
Ditto but links and stirrups, 6mm diameter at 225mm
centres, in
109
g Horizontal beams 9 kg
110
111
h Lintels(beam above the doors) 8.5 kg
112
113
Formwork to sides of Soffit and sides of beams
114
115
i Lintels(beam above the doors) and beams 2.62 m2
116
-
117
-
118
BLOCKWORK -
119
-
120
Precast sandcrete (1:6) solid blocks bedded and jointed in
cement mortar (1:6), in
121
j 150mm thick walls 50 m2
122
123
k Solid blocks 1500 m2
124
125
STONES MASONRY
126
l Precast 10-20cm stones bedded and jointed in cement
mortar (1:4), in
56.5 m3
127
m 1.4m wider ramp to reach a maximum 1m height 20.5 m3
128
n U shape side dranage of 30cm width 89 m3
129
Total Blockwork and Iron Mongery Carries to Summary -
130
3 ROOFING
131
a Zinc Alum roofing sheets 26 gauge complete with fixing
accessories
200 mm
132
b Provide and fix gutter as shown on the drawings 7 m
133
Sub Total ROOFING
134
135
WOODWORK
136
Sawn hardened timber, treated with coloured approved
wood preservatives, in
137
c 2" x 4" rafters tied from ringbeam by galvanized wired 40 m
138
139
d 2" x 3" purlins @ 1050 centres 80 m
140
141
e 2" x 6" wall plates 20 m
142
143
Wrought hardwood timber, treated with clear approved
wood preservative, in
144
f 25 x 225mm (finished) fascia/ verge board chamfer 15 m
145
146
g 2" x 8" door frames rebated 9 Nr
147
148
h Pannel Doors 9 Nr
149
150
i Welded doors and door frames 1000mm wide 1 Nr
151
152
j Tee hinges, 12" long 9 Nr
153
154
k Ram door lock (Italian type black colour) with runner
bolt with padlock externallu and runner bolt internally
9 Nr
155
Total WOODWORK and Iron Mongery Carries to Summary -
156
4 PLUMBING INSTALLATION
157
158
a PVC vent pipe, secured to wall with brackets 12 m
159
160
b 200mm diameter 3
161
162
c 200 mm diameter cowl vent 12 m
163
164
d
Provide and install 500 L water tank with all piping
connections, rain water guttering connections and fittings
on top of raised masonary platform
1 Nr
165
166
e Construct elevated masonry base to receive the PVC
water tank
1 Nr
167
Total PLUMBING CARRIES to Summary
-
168
169
5 FLOOR AND WALL FINISHINGS
170
171
Floors
172
173
Cement and sand (1:3) screed on concrete floors,
174
a 50mm thick, to receive floor tiles 25 m3
175
b ceramic floor tiles; 600mmx 600mmx80mm thick; laid in whole unit to regular pattern
on screeded floor butt jointed and grouted in white cement mortar.
70 M3
176
c ceramic wall tiles; 300mmx 300mmx60mm thickness 50 m3
177
Walls
178
Cement and sand (1:6) rendering to walls, 12mm thick
179
d Internally 80 m3
180
181
e Externally 95 m3
182
RAMP
183
Provide handrails on two sides of ramp
184
f Metal handrails Detals Referee to the drawing. 100 m3
185
TOTAL FLOORS AND WALLS FINISHINGS CARRIES TO SUMMARY -
186
187
6 PAINTING AND DECORATING
188
189
Prepare and apply three coats external quality emulsion
paint, to
190
a Externally rendered walls 48 m3
191
192
Prepare and apply three coats emulsion paint, to
193
b Internally rendered walls 46 m3
194
195
c Decorative screen blocks, both sides 25 m3
196
197
Prepare and apply three coats oil based paint to
198
d Timber batten doors including guard bars 4 m3
199
200
e Fascia board, not exceeding 300mm girth 8 m3
201
202
Total PAINTING AND DECORATING Carries to Summary -
203
204
SUBSTRUCTURE -
205
-
206
SUPERSTRUCTURE -
207
CONCRETE -
208
-
209
BLOCKWORK -
210
-
211
ROOFING -
212
-
213
WOODWORK AND IRON MONGERY -
214
-
215
PLUMBING INSTALLATION -
216
-
217
FLOOR AND WALL FINISHINGS -
218
-
219
PAINTING AND DECORATING -
220
221
Sub TOTAL for Two Rooms OFFICE -
222
223
224
TWO BEDROOMS OFFICE
225
Total
226
15% GST Included in the prices
227
GRAND TOTAL SUM INCLUDING GST SLL -
228
GRAND TOTAL SUM INCLUDING GST EU -