ABCDEF
1
: BILL OF QUANTITIES FOR CONSTRUCTION OF 3 CUBICLE LATRINE BLOCKS
2
LOCATION:Mattru JongTown Bonthe District
3
CLIENT:Action Against Hunger
4
5
Item DescriptionQtyUnitRate Amount
6
NoSLLSLL
7
(Note: All quantities are Provisional and are subject
8
to re-measurement)
9
1.0SUBSTRUCTURE
10
1.1Site Clearance
11
Clear the whole site of bushes and shrubs; remove debis
12
from site 1Item
13
1.2Excavation
14
Excavate oversite, average 150mm deep, to remove top soil5
15
1.3Excavating, starting at site strip level, maximum depth
16
not exceeding 600mm10
17
1.4Trenches to receive concrete footing in foundations10
18
1.5Excavating starting at site strip level, maximum depth
19
not exceeding 300mm
20
pit (15 Nr)20
21
1.6Excavating, rock in trenches and pit
22
latrite rocks (PROVISIONAL) 7
23
1.7gabro rocks (PROVISIONAL)7
24
SUB TOTAL -
25
FILLING AND DISPOSAL
26
Depositing and compacting in layers, maximum 200mm thick
27
1.8selected materials arising from excavations, to
28
excavations 9
29
1.9Make up levels under floors10
30
SUB TOTAL -
31
HARDCORE OR GRANULAR FILLING
32
1.10Hard Core Filling
33
making up levels; depositing and compacting in layers
34
average 150mm thick6
35
1.11Dispose of surplus excavated materials 7
36
TREATMENT OF SURFACES
37
1.12Surface Treatments
38
Surfaces of hardcore
39
blinding surface with fine graded material20m2
40
1.13Visqueen 1000g polythene damp proof membrane with
41
double welt folded joints, laid on blinded hardcre.20m2
42
1.14Level and compact the bottom of excavation9m2
43
IN- SITU CONCRETE
44
In- situ plain concrete (1:4:8 mix) ; medium workability and
45
slump to elements as per drawings
46
1.15Blinding under column pads
47
50mm thick0.75m2
48
In- situ plain concrete (1:3:6 mix) ; medium workability and
49
slump to elements as per drawings
50
1.16foundation footing , generally (150mm thick)2m3
51
In- situ Reinforced concrete,grade C2OP (1:2:4 mix) ; medium
52
workability and slump to elements as per drawings
53
1.17attached columns and bases 6m3
54
1.18septic tank slab 3m3
55
In- situ plain concrete (1:3:6 mix) ; medium workability and
56
slump to elements as per drawings
57
1.19Slab6m3
58
Ribbed high yield bar reinforcement, bent straight or hooked
59
including spacers and tying wire
60
General reinforcement
61
1.20ribbed bars; 12mm diameter1t
62
1.21ribbed bars; 6mm diameter0.5t
63
Sawn formwork
64
flat surfaces
65
1.22vertical side (columns)16m2
66
1.23vertical side (slab)14m2
67
Precast sandcrete solid block walling and jointed in
68
cement: sand motar 1.6 mix, laid in streacher bond, finished
69
smooth and pointing with flush joints both sides
70
1.24 trench 225mm thick walls 30m2
71
1.25 pit, 225mm thick walls25m2
72
1.26Finishings in Foundations
73
Cement and sand (1:6) render, smooth trowelled finish, to
74
Blockwall and concrete surfaces, 12mm thick20
75
1.27Painting in Foundations
76
Prepare and apply two coats black bituminous paint, to
77
Rendered surfaces, externally20
78
Sundries
79
1.28Disposal of water
80
keeping the surface of the site and the excavations
81
free of water1Item
82
SUBTOTAL -
83
Total SUBSTRUCTURE -
84
Carried to Summary
85
2.0BLOCKWORK
86
Precast sandcete solid block (1:6) bedded and jointed in
87
cement mortar (1:6), in
88
2.1150mm thick walls100m2
89
2.2100mm thick lourves ventilation block walls2m2
90
Total BLOCK WORK
91
Carried to Summary -
92
3.0CONCRETE WORK
93
Reinforced in-situ concrete (1:2:4-19mm aggregate), including
94
reinforcement and formwork in:
95
3.1horizontal beams1.5m3
96
3.2Lintels2.2m3
97
3.3Columns4.5m3
98
Ribbed high yield bar reinforcement, bent straight or hooked
99
including spacers and tying wire
100
General reinforcement
101
3.4ribbed bars; 12mm diameter2.5m3
102
3.5ribbed bars; 6mm diameter2m3
103
Sawn formwork
104
flat surfaces
105
3.6vertical side (columns and horizontal beams)55m3
106
Total CONCRETE WORK
107
Carried to Summary -
108
4.0ROOFING
109
Aluminium coated coloured box rib 5mm thick roofing sheet,
110
side laps of one and a half rib; 150mm end laps, fixing with
111
galvanized steel hock bolts and nuts drive screws, large
112
washer, self tapping screws, roofing bolts, nuts and clips;
113
bedding lap with approved lap sealant
114
4.1Sloping work, fixing at 1200mm centres to purlins
115
spaced at 900mm centres20m2
116
Seasoned Treated Hardwood structural Timber, size
117
4.250mm x 50mm, as
118
ceiling joists60m
119
50mm x 100mm, as
120
4.3Wall plate12m
121
4.4Rafters22m
122
50mm x 75mm, as
123
4.5purlins15m
124
4.6Struts and braces15m
125
50mm x 50mm, as
126
4.7Ceiling hangers17m
127
25mm x 225 mm as
128
4.8Ceilings work as per the instruction of the engineer. Price include supply and installation of ceilings hard board, and related carpenter works 10m2
129
4.9Fascia boards, chamfered20m
130
Total ROOFING
131
Carried to Summary -
132
5.0DOORS
133
Provide and fix the following:-
134
Standard section mild steel flush door comprising 2mm thick
135
mild steel plates on both sides 50 x 100mm RHS as frames
136
complete with heavy duty steel door lock and hinges,
137
The item includes all materials, equipment, labor and quality
138
control test according to industry & technical specifications and
139
all ancillary works needed according to the drawings and
140
instructions of the supervising Engineer, overall size:
141
5.1900mm wide x 2100mm high 3Nr
142
Ironmongery
143
5.2Brass butt hinges, 100mm9pair
144
5.3Akale Union or similar approved 75mm upright cylinder
145
mortice lock with 2-levers, complete with silver andonised
146
lever furniture.8Nr
147
Total DOORS
148
Carried to Summary -
149
6.0PLUMBING AND TILING INSTALLATION
150
Pipework, joints and support to the following cold water and
151
Sanitary installations concealed uPVC service pipework to cold
152
and sanitary installations including joints and supports to the
153
Runnings lengths, to the following:
154
6.1Supply and install a vitreous china hand washbasin with pedestal, including single lever mixer tap, waste pipe, and necessary fixings, as per specified dimensions and manufacturer's standard, complete with all necessary connections to the water supply and drainage system. 600mm x 480mm. 3 Nr
155
6.2Procure and installed with all accessories, including but not limited to, flush tanks, seats, hinges, and plumbing fittings, high-efficiency flushing mechanisms. Ensure that the installation site is adequately prepared, including the provision of necessary plumbing and drainage connections. Position the WC units according to manufacturer guidelines and specifications. Connect to the water supply and drainage systems, ensuring no leaks or obstructions in flow. Install and test the flushing system to ensure proper operation. 3 Nr
156
Total PLUMBING -
157
Carried to Summary
158
7.0FLOOR AND WALLS FINISHINGS
159
Floor
160
7.1Cement and sand (1:3) screed on concrete floors,
161
50mm thick, to receive floor tiles15
162
7.2Ceramic floor tiles; 300mm x 300mm x 8mm thick; laid in
163
whole unit to regular pattern on screeded floor butt jointed
164
and grouted in white cement mortar15
165
Walls
166
Cement and sand (1:6) rendering to walls,12mm thick,
167
7.3internally75m2
168
7.4 externally 75m2
169
7.5White glazed ceramic wall tiles, 150mm x 150mm x 6mm thick;
170
1500mm high,fixed vertically to walls in regular pattern with
171
ceramic tile fixer and jointed in white cement.25
172
Total FINISHINGS
173
Carried to Summary -
174
8.0PAINTING AND DECORATTING
175
Prepare and apply three coats external quality emulsion paint,to
176
8.1externally rendered walls90liter
177
Prepare and apply three coats emulsion paint, to
178
8.2internally rendered walls and ventilation block wall 108liter
179
Prepare and apply three coats oil based paint, to
180
Total PAINTING
181
Carried to Summary -
182
183
184
Item Amount
185
NoSLL
186
SUMMARY
187
188
POUR FLUSH TOILET
189
190
1.0SUBSTRUCTURE -
191
192
2.0BLOCK WORK -
193
194
3.0CONCRETE WORK -
195
196
4.0ROOFING -
197
198
5.0DOORS -
199
200
6.0PLUMBING AND TILING INSTALLATION -
201
202
7.0FLOOR AND WALLS FINISHINGS -
203
204
8.0PAINTING AND DECORATION -
205
SUB-TOTAL -
206
207
208
Total cost including GST -
209
210
211
212